Work to raise dam in Seychelles 25 percent complete - but 4 months behind schedule

Renovation work to raise Seychelles’ main water reservoir – La Gogue Dam – in order to increase its capacity is 25 percent complete, but the project is four months behind schedule because of a strike by truckers, the chief executive of the Public Utilities Corporation (PUC) said.

Work on the dam, which was built in 1969 in the northern Mahe district of Anse Etoile, will raise it six metres and increase its storage capacity by 60 percent.

PUC Chief Executive Philippe Morin was speaking to journalists following a site visit by President Danny Faure, last Friday. The project which was expected to end this year is now delayed and its completion is due in the first quarter of 2020.

“The project has been delayed by approximately four months and 10 days; four months when local truckers went on strike and 10 days due to unfavourable weather conditions,” said Morin.

“That has been resolved so we are all working to ensure that the project is completed by the expected time in March or April 2020. For the time being, the majority of the work is concentrated on the embankment which is the mound of various compositions of soil, sand, clay or rock and acts like a wall,” explained the chief executive.

According to Morin the dam currently stands at 144 metres in height and will measure approximately 151 metres once work is completed.

That will increase the reservoir's capacity by 600,000 cubic metres, making its total storage capacity 1.6 million cubic metres. Among the facilities to be installed will be a new water treatment plant with the capacity of treating 4,400 cubic metres of water per day that will help to ensure sufficient water supply for the northern region.

The project which started in November 2017 is being undertaken by the Sinohydro Corporation, a Chinese company based in Mauritius.

Morin said that an imperative phase of the project requires the dam to be completely drained to allow for pipes and other fixtures to be replaced and fitted. This is expected to be done by the middle of this year.

The dam is the principal source of water supplied to the north and central regions of the main island of Mahé but it also supplies water to other regions when necessary.

According to the chief executive, PUC has been working on the preparatory phases within the last two or three years to ensure that they have an adequate supply of water for the duration of time when the dam is drained.

 “We expect that around June or July this year, the water level in the dam will be at almost zero percent to reinforce the embankment both from the inside and out. We also need to change all the pipes from the dam downwards and replace equipment and fixtures,” Morin added.

During that time water will be distributed from other freshwater sources including the Rochon dam, as well as the Hermitage, Le Niole, Cascade treatment plants.

The company also intends to increase the daily capacity of desalinated water by 4,000 cubic metres to increase supply when the reservoir is drained so as not to put a strain on other existing water supply.

Currently, there are four desalination plants on the main island of Seychelles – a group of 115 islands in the western Indian Ocean.

Forrás: www.seychellesnewsagency.com

Megosztás
GACOR77 CAIR77 ADMIN77 DP96 RUPIAH138 RECEH88 RECEH88 MANTUL138 MANTUL138 PASUKAN88 PASUKAN88 BOBO77 BAYAR77 BAYAR77 GARUDA69 RUPIAH138 GCR77 TANGO77 GACOR77 GACOR77 MODUS99 LORD88 GOCAP123 GACOR96 ODIN77 PARGOY88 PARGOY88 MAXWIN138 MAXWIN138 MAXWIN138 POLASLOT138 EPICWIN138 DISKO69 NGASO77 WIBU69 BESTI69 DINO69 BOSSWIN168 BOSSWIN168 RECEH69 MEWAHBET MEWAH99 FOYA88 SAWER138 PUAS69 MIDAS77 MIDAS77 SIP69 SIP69 MODUS99 MODUS99 GCR77 MASTER38 MABAR69 LOTUS138 LOTUS138 COCOL88 BARON69 DINASTI168 ZONA69 NOBAR69 RONIN86 STARLING69 DAGET77 DAGET77 ADMIN77 GARUDA69 PAY77 PAY77 MEMBER77 MEMBER77 BANK77 BANK77
MIDAS77 TOKO79 ONLINE138 WA77 BANK77 GCR77 DETIK123 PECAH138 SIAP46 JUS77 OJOL77 SIP69 MODUS99 LOTUS138 DINASTI168 ZONA69 NOBAR69 RONIN86 BARON69 STARLING69 MABAR69 BOBO77 MAHJONG69 MASTER38 COCOL88 BOSSWIN168
BOSSWIN168 BOSSWIN168 BOSSWIN168 BOSSWIN168 https://pol-ka.com/ http://saint-ex.com/ https://bego.hu/ https://planetexpo.fr/author/geoffrey/ https://planetexpo.fr/bijoux https://www.fromfailuretopromise.com/about-dr-c/ https://www.kubeval.com/ls168/ https://gansossalvajes.com/account/login/ https://www.antiracket.info/account/login https://www.stratfordbikehire.com/Bikes/ https://microxchg.io/bobo/ https://testmyquiz.com/cocol88/ https://www.dreamgreen.earth/cocol/ https://gansossalvajes.com/account/login/ https://gansossalvajes.com/ https://turbokolor.com/about2a05.html https://bosswwin168.locker/ COCOL88 COCOL88 COCOL88 COCOL88 COCOL88 COCOL88 MASTER38 MASTER38 BOSSWIN168 HITAM138 slot online game online gacor77 egp88 game gacor fix77 new77 gacor96 sikat88 online138 siap46 qris bayar77 BAYAR77 SIKAT88 slot gacor https://www.havetrestaurant.no/meny https://sessiondesign.ru/bosswin168/ https://carriecollections.com/product/gacor77/ https://eldoradoklub.org/ https://new6s.be/soutiens/ https://www.ramlinestocks.com/contact_us.html
MAHJONG69 NOBAR69 COCOL88 LIVESLOT168 MASTER38 MASTER38 https://luckypatcher.com.mx/descargar/
KFCSLOT UBER77 ONLINE138 PECAH138 SIAP46 DANA69 JUS77 WIBU69 PARGOY88 EPICWIN138 GACOR77 GACOR77 JEPE77 WEB77 slot gacor slot qris game online DINASTI168 LOTUS138 BOSSWIN168
LOGIN JURAGAN69 LOGIN BAYAR77 LOGIN DANA69 LOGIN EGP88 LOGIN SIP69 LOGIN KOIN138 LOGIN NONGKI99 LOGIN MAHJONGWAYS LOGIN BAKAR77 LOGIN COCOL88 LOGIN MAHJONG69 LOGIN MEMBER77 LOGIN BANK77 LOGIN PAY77 LOGIN RONIN86 DINASTI168 LOTUS138 BESTI168 DISKO69 MAXWIN138 POLASLOT138 PARGOY88 DINO69 EPICWIN138 HAHA69 NGASO77 GARUDA69 GARUDA138 SIP69 GACOR77 MAHJONG69 RONIN86 MABAR69 COCOL88 BOSSWIN168 MASTER38 NOBAR69 ZONA69 BARON69 BOBO77 STARLING69 SIKAT88 STARS77 AGEN138 DANA69 KOPI77 OJOL77 WEB77 MIDAS77 EGP88 FIRE138 BAYAR77 PAY77 BANK77 ADMIN77 BUKA77 MENANG77 MEMBER77 WA77 TOKO79 MODUS99 WD138 PECAH138 GACOR96 GANAS69 ONLINE138 JUS77 SIAP46 VICTORY77 ODIN77 ML138 DETIK123 RUPIAH138 GCR77 DP96 CAIR77 RECEH88 MANTUL138 PASUKAN88 FOYA88
MASTER38 MASTER38 MASTER38 MASTER38 BOSSWIN168 BOSSWIN168 BOSSWIN168 BOSSWIN168 BOSSWIN168 COCOL88 COCOL88 COCOL88 COCOL88 MABAR69 MABAR69 MABAR69 MABAR69 MABAR69 MABAR69 MABAR69 MAHJONG69 MAHJONG69 MAHJONG69 MAHJONG69 RONIN86 RONIN86 RONIN86 RONIN86 RONIN86 RONIN86 RONIN86 RONIN86 ZONA69 ZONA69 ZONA69 NOBAR69 ROYAL38 ROYAL38 ROYAL38 ROYAL38 ROYAL38 ROYAL38 ROYAL38 ROYAL38
SLOT GACOR HARI INI SLOT GACOR HARI INI